Monthly Report

Report Date
September 2017
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
The AV contractor has partially installed. Waiting on outstanding equipment.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CAHSS DRU V3.1 55GS Rm1.04
Code
AV2707
Programme
ISG Learning and Teaching Spaces: CAHSS (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Richard Lomax
Current Stage
Close
Status
Closed
Start Date
18-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Sep-2017