Monthly Report

Report Date
August 2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Teaching Accommodation Programme 2019
Code
AV2805
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
Stephen Carter
Project Sponsor
Gillian Nicoll
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Oct-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Aug-2019
Overall Priority
Normal
Category
Compliance

Documentation

Not available.