Project Status Reports

Title Report Date Time Cost Scope Overall Change
Monthly Report July 2019 GREEN GREEN GREEN GREEN No Change
Monthly Report June 2019 GREEN GREEN GREEN GREEN No Change
Monthly Report May 2019 GREEN GREEN GREEN GREEN No Change
Monthly Report March 2019 GREEN GREEN GREEN GREEN No Change
Monthly Report November 2018 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Kennedy Tower LT1
Code
AV2809
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
Eddy O'Hare
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Nov-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Sep-2019
Overall Priority
Normal
Category
Compliance

Documentation