Monthly Report

Report Date
March 2020
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Low importance so we have suspended this until later in the year.
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
Significant
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
59 George Square G.09
Code
AV2884
Programme
ISG Learning and Teaching Spaces: CAHSS (AV)
Management Office
ISG PMO
Project Manager
Guy Tittley
Project Sponsor
Richard Lomax
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
13-Feb-2020
Planning Date
n/a
Delivery Date
11-Sep-2020
Close Date
10-Sep-2021
Overall Priority
Normal
Category
Compliance

Documentation

Not available.