Upgrading the equipment in 2 spaces with digital equipment and repeater screen.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2020 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
CSE StEAP - JCMB 6231 & 6307
Code
AV2887
Programme
ISG Learning and Teaching Spaces: CSE (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Victoria Dishon
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Mar-2020
Planning Date
n/a
Delivery Date
11-Sep-2020
Close Date
30-Sep-2020
Overall Priority
Normal
Category
Compliance

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard