Project Status Reports

Title Report Date Time Cost Scope Overall Change
Monthly Report June 2022 GREEN GREEN GREEN GREEN No Change
Monthly Report May 2022 GREEN GREEN GREEN GREEN No Change
Monthly Report April 2022 GREEN GREEN GREEN GREEN No Change
Monthly Report March 2022 GREEN GREEN GREEN GREEN No Change
Monthly Report February 2022 GREEN GREEN GREEN GREEN No Change

Project Info

Project
SoEngineering 2022 AV Upgrades
Code
AV2945
Programme
ISG Learning and Teaching Spaces: CSE (AV)
Management Office
ISG PMO
Project Manager
Richard Leslie
Project Sponsor
Fraser Millar
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Feb-2022
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2022
Overall Priority
Normal
Category
Compliance

Documentation