Skip to main content
Toggle section links
Views
Projects
Programmes
Portfolios
Requests
New Project
New Programme
New Portfolio
Help
Schools & departments
MyEd
Search:
Search
Easter Bush 1.21 AV work
Easter Bush 1.21 AV work
Home
Projects
Easter Bush 1.21 AV work
Status
Monthly Report
Monthly Report
Report Date
February 2023
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on
Feb 28, 2023
Project Info
Project
Easter Bush 1.21 AV work
Code
AV2986
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
Richard Leslie
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Sep-2022
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Sep-2023
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Not available.