Monthly Report

Report Date
February 2023
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Easter Bush 1.21 AV work
Code
AV2986
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
Richard Leslie
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Sep-2022
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Sep-2023
Overall Priority
Normal
Category
Compliance

Documentation

Not available.