Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2023 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Bayes BYoD USB switching
Code
AV3026
Programme
ISG Learning Spaces Technology (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Natalia Gibczynska
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-May-2023
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jun-2023
Overall Priority
Normal
Category
Compliance

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.