Appleton Tower AV Reinstatement - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2024 AMBER 0.0 days 0.0 days 0.0
Content
Status
Withdrawn
Current Stage
Procure
Start Date
Thursday, 1 August 2024
Close Date
Thursday, 31 October 2024
Project information
Project Code
AV3040
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Session
24/25
23/24
Organisational Unit
Learning Teaching and Web
Project Management Office (if relevant)
ISG PMO
Responsibility
Learning Teaching and Web
Project Category
Compliance
Project Classification
Run
Project Type
Infrastructure
Project Size
Medium
Funding Source
Estates
Overall Priority
Normal
Student Impact
Project deliverables will be used by staff on behalf of students