Project Status Reports

Title Report Date Time Cost Scope Overall Change
Monthly Report April 2025 GREEN GREEN GREEN GREEN Within Tolerance
Monthly Report March 2025 GREEN GREEN GREEN GREEN Within Tolerance
Monthly Report February 2025 RED GREEN RED RED No Change
Monthly Report January 2025 AMBER GREEN RED RED Significant
Monthly Report July 2024 AMBER GREEN GREEN AMBER Moderate
Monthly Report June 2024 AMBER GREEN GREEN AMBER Moderate

Project Info

Project
Appleton Tower AV Reinstatement
Code
AV3040
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
Richard Leslie
Project Sponsor
GORDON McDougall
Current Stage
Integrate
Status
In Progress
Project Classification
Run
Start Date
01-Aug-2024
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2025
Overall Priority
Normal
Category
Compliance

Documentation

Not available.