Title Report Date Time Cost Scope Overall Change
Monthly Report August 2024 GREEN GREEN GREEN GREEN No Change
Monthly Report July 2024 GREEN GREEN GREEN GREEN No Change
Monthly Report June 2024 GREEN GREEN GREEN GREEN No Change
Monthly Report May 2024 GREEN GREEN GREEN GREEN No Change
Monthly Report April 2024 GREEN GREEN GREEN GREEN Within Tolerance
Monthly Report March 2024 GREEN GREEN GREEN GREEN Within Tolerance

Project Info

Project
Appleton Tower 2.12 & 2.14
Code
AV3057
Programme
ISG Learning and Teaching Spaces (LTS)
Management Office
ISG PMO
Project Manager
Richard Leslie
Project Sponsor
Lesley Greer
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
01-Mar-2024
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Sep-2024
Overall Priority
Normal