Monthly Report

Report Date
September 2024
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MVM - Medical Quad TR10 & TR11
Code
AV3067
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
David Whitaker
Project Sponsor
Alan Gilchrist
Current Stage
Integrate
Status
In Progress
Project Classification
Transform
Start Date
01-Mar-2024
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2024
Overall Priority
Normal

Documentation

Not available.