October 2020 Update

Report Date
October 2020

Funding secured from CRDEGG, enabling full roll out of extended operations team model (including events capacity).  Whilst this is still subject to the completion of the people mapping processes, this should now be considered to be complete - with resource secure, job descriptions signed off (and graded) and the Service Manager due to arrive on 7th January 2021. 

Project Status
RAG Status
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Integration of staff resource across Bayes sub-teams (including agreed core responsibilities and ways of working)
Code
BAY406
Programme
Bayes Centre Operations (BCO)
Project Manager
Neil McGillivray
Project Sponsor
Michael Rovatsos
Current Stage
Close
Status
Closed
Start Date
06-Jan-2020
Planning Date
n/a
Delivery Date
18-Dec-2020
Close Date
07-Nov-2020
Overall Priority
Normal