The Access Control Doors service’s central infrastructure has hosted the CCURE 800 application for several years.
The physical host machines are at the end of their operating life. The application needs to be upgraded to enable more capable controller equipment to be deployed and to enable the service to be managed more effectively.
A procurement (Phase 1 of this project) was undertaken in latter part of the 2016-17 UoE financial year resulting in Evolution (Electronic Security Systems) Ltd being selected to upgrade the service to CCURE 9000.
Phase 2 of the project is to upgrade the service from CCURE 800 to CCURE 9000 and perform service improvements where there are opportunities to do so.
The project has a SharePoint site here.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
July 2019 | BLUE | 50.0 days | 208.0 days | 0.0 |