The Access Control Doors service’s central infrastructure has hosted the CCURE 800 application for several years.

The physical host machines are at the end of their operating life.  The application needs to be upgraded to enable more capable controller equipment to be deployed and to enable the service to be managed more effectively. 

A procurement (Phase 1 of this project) was undertaken in latter part of the 2016-17 UoE financial year resulting in Evolution (Electronic Security Systems) Ltd being selected to upgrade the service to CCURE 9000.

Phase 2 of the project is to upgrade the service from CCURE 800 to CCURE 9000 and perform service improvements where there are opportunities to do so.

The project has a SharePoint site here.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2019 BLUE 50.0 days 208.0 days 0.0

Project Info

Project
Access Control Door Infrastructure Upgrade - Procure and Install
Code
CIS003
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Karen Wilson
Project Sponsor
Dave Graham
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
03-Apr-2017
Planning Date
12-Mar-2018
Delivery Date
28-Jun-2018
Close Date
07-Aug-2019
Overall Priority
Highest
Category
Compliance

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.