Second Draft IT Infrastructure Standard document completed

Second draft of Standards document received.

George R. now revising his document, and looking for comeone to replace George L.

Objective is to make this the Master Copy to be in use by AH team by March

 

Our problem is to find a replacement for George - contacting Apps in the first instance if Gavin okays expinditure

 

 

Project Info

Project
Standard Template for IT New Builds and Refurbishments.
Code
CIS005
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
02-Nov-2015
Planning Date
27-Nov-2015
Delivery Date
23-Aug-2018
Close Date
27-Aug-2018
Overall Priority
Higher
Category
Discretionary