Impact

 

Priority and Funding

This project is a High Priority project within the ITI Communications Infrastructure programme. ITI resources are available and commited to the project, and ITI have secured an external expert as the Technical Author.

We will only proceed with commitment of people from Estates and LTW and USD.

 

Impact and Dependencies

There is a dependency of having the IT Standards document ready in time to be useful to the AH refurbishment.

The IS Standards document that will feed into the Network Strategy Review project starting this year.

 

Constraints

The technical author has been contracted for twomonths (40 days) so completing the second draft must be done by mid-January.
 

Tolerances and Governance

There are no specific limits set in terms of resource.

Issues regarding ITI people resource and contractor funding will be escalated to Senior Supplier, Alan Boyd. Given the importance of having the documents ready as soon as possible for use on Argyle House, any slippage of milestones impacting on agreed delivery dates to be escalated immediately to sponsor Tony as soon as it is known, with any action to resolve the issue identified.

 

Collaboration

The project team will use the projects website for project transparency and information.

A wiki space will be used to provide a space for collaboration.

 

Lessons Learned

See Lesson Learned (wiki supporting pages) for lessons logged during project and outcomes.

Project Info

Project
Standard Template for IT New Builds and Refurbishments.
Code
CIS005
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
02-Nov-2015
Planning Date
27-Nov-2015
Delivery Date
23-Aug-2018
Close Date
27-Aug-2018
Overall Priority
Higher
Category
Discretionary