Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for August 2018 August 2018 GREEN GREEN GREEN BLUE
Report for July 2018 July 2018 GREEN GREEN GREEN GREEN
Report for June 2018 June 2018 AMBER GREEN GREEN AMBER
Report for May 2018 May 2018 GREEN GREEN GREEN GREEN
Report for April 2018 April 2018 GREEN GREEN GREEN GREEN
Report for March 2018 March 2018 AMBER GREEN GREEN AMBER
Report for February 2018 February 2018 GREEN GREEN GREEN GREEN
Report for January 2018 January 2018 GREEN GREEN GREEN GREEN
Report for December 2017 December 2017 GREEN GREEN GREEN GREEN
Report for November 2017 November 2017 GREEN GREEN GREEN GREEN
Report for October 2017 October 2017 GREEN GREEN GREEN GREEN
Report for August 2017 August 2017 RED GREEN GREEN RED
Report for July 2017 July 2017 RED GREEN GREEN RED
Report for June 2017 June 2017 RED GREEN GREEN RED
Report for May 2017 May 2017 RED GREEN GREEN RED
Report for April 2017 April 2017 AMBER GREEN GREEN AMBER
Report for March 2017 March 2017 GREEN GREEN GREEN GREEN
Report for February 2017 February 2017 GREEN GREEN GREEN AMBER
January 2017 January 2017 GREEN GREEN GREEN GREEN
November 2016 November 2016 RED GREEN GREEN RED
October 2016 October 2016 GREEN GREEN GREEN GREEN
September 2016 September 2016 GREEN GREEN GREEN GREEN
August 2016 August 2016 AMBER GREEN GREEN AMBER
July 2016 July 2016 RED RED GREEN RED
June 2016 June 2016 AMBER GREEN GREEN AMBER
May 2016 May 2016 GREEN GREEN GREEN GREEN
April 2016 April 2016 GREEN GREEN GREEN GREEN
March 2016 March 2016 GREEN GREEN GREEN GREEN
February 2016 February 2016 GREEN GREEN GREEN GREEN
January 2016 January 2016 GREEN GREEN GREEN GREEN
December 2015 December 2015 GREEN GREEN GREEN GREEN
November 2015 November 2015 GREEN GREEN GREEN GREEN
October 2015 October 2015 GREEN GREEN GREEN GREEN

Project Info

Project
Standard Template for IT New Builds and Refurbishments.
Code
CIS005
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
02-Nov-2015
Planning Date
27-Nov-2015
Delivery Date
23-Aug-2018
Close Date
27-Aug-2018
Overall Priority
Higher
Category
Discretionary