Replacement of firewalls or implementation of additional enhanced security. This project has now been withdrawn and added to the scope of CIS009 - Network Refresh.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
February 2018 | BLUE | 20.0 days | 1.0 day | 0.0 |