Project on track
- Report Date
- December 2017
Summary
Project on track
Achievements in Last Period
- Draft matrix created for Firewall requirements to compare products / brands
Issues and Risks
- none
Next Steps
- Final matrix and specification to be produced
- Review CCS framework catalogue to see if off-the-shelf product available
Future Milestones
Target Date![]() |
Previous Date | Title | Stage | Complete | |
---|---|---|---|---|---|
26-Jan-2018 | No date available | Project plan agreed | Plan | No | |
26-Jan-2018 | No date available | Matrix of Firewall Options complete | Plan | No | |
23-Feb-2018 | No date available | Product Options Defined | Plan | No | |
30-Mar-2018 | No date available | Procurement | Procure | No |
- Approved budget
- 20.0 days
- Activity this month
- 0.5 days
- Activity this year
- 0.5 days
- Activity to date
- 0.5 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 19.5 days