The University of Edinburgh has procured hardware, software and services to replace the majority of its data network infrastructure, including the current ResNet network which services the University's residential estate operated by Accommodation, Catering and Events (ACE).

The project implementation period is expected to be 24 months from award of contract, and the scope of the project will include replacement of the following:-

  • Central Technologies (border, core, distribution and edge layer infrastructure)
  • Wireless LAN (WLAN) infrastructure
  • Perimeter and internal firewalls
  • Network Security Controls
  • Network Management and Monitoring Systems
  • Maintenance & support services

Other components of the data network infrastructure (including guest wireless facilities and additional network security controls) may also be incorporated over the course of the initial 5 year term of contract where additional service advantage is achieved.

This project will impact all areas of the University and will be planned and managed to minimise disruption to staff, students and services during the implementation period, and regular communications will be carried out to ensure everyone is well informed.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2021 GREEN 450.0 days 216.5 days 270.5

Project Info

Project
Network Infrastructure Deployment
Code
CIS014
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Rick Arnautovic
Project Sponsor
Anthony Weir
Current Stage
Integrate
Status
In Progress
Project Classification
Transform
Start Date
07-Jan-2019
Planning Date
31-Oct-2019
Delivery Date
30-Dec-2021
Close Date
30-Jan-2022
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation

Not available.