Organisation

 

Work/Task Breakdown

TaskTeam
FamiliarisationDevTech
* Firewall prepDevTech
* DB UpgradeDevTech
TAD UpdateDevTech
* Assist Serengeti during upgradeDevTech
* EBIS configuration changesDevTech
* EFIN configuration changesApps Mgt
Scanner configurationApps Mgt / PS
Operational documentationDevTech
Assist UATService Mgt
Review DRDevTech

*Tasks will be repeated on each environment

The estimate at end of planning is 86 days as detailed in the 3 point estimate spreadsheet

Project Info

Project
Upgrade Document Management System
Code
CMW010
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
03-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance