Report for January

Report Date
January 2015

 

Achievements

  • Configuration changes applied
  • Deployment Review sign off achieved

Issues

  • After more system instability, Serengeti identified configuration settings that were not picked up by the start scripts, these were subsequently 

Next Steps

  • Close project
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
117.0 days
Activity this month
5.0 days
Activity this year
51.0 days
Activity to date
115.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrade Document Management System
Code
CMW010
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
03-Feb-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance