Library General Collections Strategy - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2023 BLUE 20.0 days 16.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Thursday, 24 November 2022
Planning Date
Wednesday, 18 January 2023
Delivery Date
Friday, 21 July 2023
Close Date
Thursday, 3 August 2023
Project information
Project Code
COLL002
Programme
ISG – Collections 2025 (COLL)
Session
23/24
22/23
Organisational Unit
Library and University Collections
Project Management Office (if relevant)
ISG PMO
Responsibility
Library and University Collections
Project Category
Discretionary
Project Classification
Transform
Project Type
Business Case
Project Size
Small
Project Complexity
Simple
Alignment to Strategy 2030 and Adaptation & Renewal Team (ART)
Research
Teaching and Learning
Funding Source
Sponsor
Programme Priority
2
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students