This is a pilot project to engage with 3 schools (one for each college) to create a development plan to increase resource list usage to 90% and link into Curriculum Transformation programme.

The development plan / lessons learned will be used to rollout resource lists across the university post 2024

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2024 BLUE 20.0 days 21.0 days 0.5

Project Info

Project
Resource List Development Plan Pilot
Code
COLL005
Programme
ISG – Collections 2025+ (COLL)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Hannah Mateer
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
31-Jul-2023
Planning Date
04-Oct-2023
Delivery Date
30-Sep-2024
Close Date
31-Oct-2024
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.