Report for July 2024
- Report Date
- July 2024
Achievements in Last Period
- Work has continued on the various surveys, with the majority now complete ahead of project closure
- 'In progress' surveys taken as far as possible - these require further assessment to complete
- Survey in General Collections L01 requires an Asian language specialist to complete
- Draft closure report circulated and updated after comments received from team
Issues
- Site library surveys not complete by end of July (as anticipated). These will be incorporated into 'business as usual' work.
- Effort for project management revised to total of 12 days. Change control approved.
Next Steps
- Complete sign-off of closure report and formally close project.
The project status is GREEN
Milestone | Due Date |
---|---|
Closure |
31-Jul-2024
|
- Approved budget
- 12.0 days
- Activity this month
- 3.0 days
- Activity this year
- 12.0 days
- Activity to date
- 12.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days