Report for October 2012
- Report Date
- October 2012
Achievements in Last Period
The remaining scanner client was installed in Finance and is now ready for production. Delivery sign off was received from all Stakeholders.
Issues
No additional issues to report.
Next Steps
Project will move to closure.
Milestones
Target date | Title |
---|---|
07-Nov-2012 | Closure |
- Approved budget
- 49.0 days
- Activity this month
- 1.6 days
- Activity this year
- 7.4 days
- Activity to date
- 46.8 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days