Report for October 2012

Report Date
October 2012

Achievements in Last Period

The remaining scanner client was installed in Finance and is now ready for production. Delivery sign off was received from all Stakeholders.

Issues

No additional issues to report.

Next Steps

Project will move to closure.

Milestones

Target dateTitle
07-Nov-2012Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
49.0 days
Activity this month
1.6 days
Activity this year
7.4 days
Activity to date
46.8 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Kofax Upgrade
Code
COM002
Programme
Z. Communication, Media and Web (CMW) (Closed 31/07/14)
Project Manager
Tim Gray
Project Sponsor
Mark Wetton
Current Stage
Close
Status
Closed
Start Date
19-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a

Documentation