November 2012
- Report Date
- November 2012
Achievements in Last Period
No work has been completed this month, closure has been moved out to December due to resource availability in Project Services.
Issues
No additional issues to report.
Next Steps
Project will move to closure.
Milestones
Target date | Title |
---|---|
07-Dec-2012 | Closure |
- Approved budget
- 49.0 days
- Activity this month
- 0.1 days
- Activity this year
- 7.4 days
- Activity to date
- 46.9 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days