The COM004 project seeks to fix IDM Aging performance problems. The IDM Aging suite was not implemented when IDM went live due to performance issues. This project will specifically look to tune the performance of aspects of the code and amend functionality to allow the current backlog of 27,007 affiliations to be addresed over a period of months and , thereafter , allow the Aging suite to run overnight as intended , ensuring update affilitions and completed notifications on a nightly basis.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
January 2013 | BLUE | 30.0 days | 29.7 days | 0.0 |