Report for November 2012

Report Date
November 2012

Achievements in Last Period

  • Tuning areas defined.
  • Coding Completed and Added to TEST
  • Testing completed and deployment to LIVE completed on the 5th

Issues

  •  No issues

Next Steps

  • DSOR and Project Closure

 

Target dateTitle
28-Nov-2012Sign Off Brief and Plan
04-Dec-2012ASOR
05-Dec-2012Deploy to LIVE
19-Dec-2012DSOR/Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
19.5 days
Activity this month
15.0 days
Activity this year
15.0 days
Activity to date
15.0 days
Estimate to complete current year
4.5 days
Estimate to complete future years
0.0 days

Project Info

Project
IDM Ageing
Code
COM004
Programme
Z. Communication, Media and Web (CMW) (Closed 31/07/14)
Project Manager
Stephen Conlon
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
12-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Feb-2013