Report for November 2012
- Report Date
- November 2012
Achievements in Last Period
- Tuning areas defined.
- Coding Completed and Added to TEST
- Testing completed and deployment to LIVE completed on the 5th
Issues
- No issues
Next Steps
- DSOR and Project Closure
Target date | Title |
---|---|
28-Nov-2012 | Sign Off Brief and Plan |
04-Dec-2012 | ASOR |
05-Dec-2012 | Deploy to LIVE |
19-Dec-2012 | DSOR/Closure |
- Approved budget
- 19.5 days
- Activity this month
- 15.0 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 4.5 days
- Estimate to complete future years
- 0.0 days