Report for September 2014

Report Date
September 2014

Achievements this period

 

New budget agreed and milestones agreed.

TEST environment  be delivered and signed off.

TAD  completed.

 

Next Steps

 

Project to close.

 

Milestones

27-Oct-201425-Jul-2014Closure

 

 

RAG Status

The project is GREEN

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
450.0 days
Activity this month
11.0 days
Activity this year
20.0 days
Activity to date
440.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days