Replace the legacy committee intranet application with a solution based on a centrally-supported platform, including

·         Researching requirements for committee support

·         Semi-automated migration solution for committees

·         Sharepoint template or site/sub-site structure

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2016 BLUE 132.0 days 135.0 days 1.0

Project Info

Project
Committee Intranet Replacement
Code
COM016
Programme
ISG - Communication (COM)
Project Manager
Tim Gray
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
01-Dec-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Apr-2016
Category
Discretionary