Organisation

Work/Task Breakdown

Planning

Preparation of project brief

Business Analysis

Investigate Service Selection screen checkbox combination options

Investigate Search screen for keeping required fields and removing others

Investigate Input screen for keeping required fields and removing others

Systems Design

Update TAD

Build

Changes to the service selection screen

Changes to the UI to allow different selection criteria selecting the right combination of services

Removal of some redundant information collection from input screens

Rework

Documentation

Peer testing

Integration

Deploy to test

Integration testing

Acceptance

UAT

Development Support

Deployment Checklist

Deployment

Deploy to Live

Development Support

Handover to Production

Closure

Closure documentation

Resources Skills and Cost

Project Info

Project
VRS Improvements
Code
COM018
Programme
ISG - Communication (COM)
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
09-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Dec-2015
Overall Priority
Normal
Category
Discretionary