Report for April 2015
- Report Date
- April 2015
Achievements in Last Period
- SDS completed
- Requirements review signed off
- Development started
Issues
- Continued developer conflict with LMP004
- Build dates at risk
- Project manager due to go on paternity leave at end of May
Next Steps
- Continue the build with the pockets of development available, currently estimated at 1.5 days per week.
- Review and possibly extend the remaining milestones if development slips.
- Approved budget
- 50.0 days
- Activity this month
- 4.7 days
- Activity this year
- 23.6 days
- Activity to date
- 23.6 days
- Estimate to complete current year
- 26.4 days
- Estimate to complete future years
- 0.0 days