Report for April 2015

Report Date
April 2015

Achievements in Last Period

  • SDS completed
  • Requirements review signed off
  • Development started

 

Issues

  • Continued developer conflict with LMP004
  • Build dates at risk 
  • Project manager due to go on paternity leave at end of May

 

Next Steps

  • Continue the build with the pockets of development available, currently estimated at 1.5 days per week.
  • Review and possibly extend the remaining milestones if development slips.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
4.7 days
Activity this year
23.6 days
Activity to date
23.6 days
Estimate to complete current year
26.4 days
Estimate to complete future years
0.0 days

Project Info

Project
VRS Improvements
Code
COM018
Programme
ISG - Communication (COM)
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
09-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Dec-2015
Overall Priority
Normal
Category
Discretionary