Report for June 2015

Report Date
June 2015

Achievements in Last Period

  • Build completed
  • Integration and acceptance testing started

 

Issues

  • Holidays delaying project. Will have a period of no activity in July and August before deployment to live

 

Next Steps

  • Complete Integration and acceptance testing
  • Resourcing secured for August deployment
  • Deployment, DSOR and project closure

 

Milestones

10-Jul-2015Integration sign off review
17-Jul-2015Acceptance sign off review
25-Aug-2015Deployment
08-Sep-2015Deployment sign off review
15-Sep-2015Project closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
9.9 days
Activity this year
41.9 days
Activity to date
41.9 days
Estimate to complete current year
3.5 days
Estimate to complete future years
4.9 days

Project Info

Project
VRS Improvements
Code
COM018
Programme
ISG - Communication (COM)
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
09-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Dec-2015
Overall Priority
Normal
Category
Discretionary