Report for July 2015

Report Date
July 2015

Achievements in Last Period

  • Resourcing secured for fixes to JIRAS for Integration testing sign off and Deployment after Special CAB period
  • Currently in a period of no activity during July due to developer being on extended leave

 

Issues

  • No issues during July

 

Next Steps

  • Fixes to outstanding JIRAs on developer's return
  • Integration Testing signoff

 

Milestones

28-Aug-2015Integration sign off review
18-Sep-2015Acceptance sign off review
30-Sep-2015Deployment
14-Oct-2015Deployment sign off review
23-Oct-2015Project closure

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
50.0 days
Activity this month
4.1 days
Activity this year
48.2 days
Activity to date
48.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
20.0 days

Project Info

Project
VRS Improvements
Code
COM018
Programme
ISG - Communication (COM)
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
09-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Dec-2015
Overall Priority
Normal
Category
Discretionary