Report for July 2015
- Report Date
- July 2015
Achievements in Last Period
- Resourcing secured for fixes to JIRAS for Integration testing sign off and Deployment after Special CAB period
- Currently in a period of no activity during July due to developer being on extended leave
Issues
- No issues during July
Next Steps
- Fixes to outstanding JIRAs on developer's return
- Integration Testing signoff
Milestones
28-Aug-2015 | Integration sign off review |
18-Sep-2015 | Acceptance sign off review |
30-Sep-2015 | Deployment |
14-Oct-2015 | Deployment sign off review |
23-Oct-2015 | Project closure |
- Approved budget
- 50.0 days
- Activity this month
- 4.1 days
- Activity this year
- 48.2 days
- Activity to date
- 48.2 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 20.0 days