August 2015
- Report Date
- August 2015
Achievements in Last Period
- Jiras fixed for integration sign off
Issues
- Senior Management require that the technical service headings in VRS are replaced with user orientated services as used in the service catalogue. This abstraction layer needs to be mapped to corresponding technical services in the IDM as well as email triggers where necessary. This has now held up the integration sign off and pushed the milestones out
- Budget increase of 5 days required to carry out the scope change
Next Steps
- Updates to service selection
- Integration Testing signoff
- Deployment sign off
Milestones
18-Sep-2015 | Acceptance sign off review |
30-Sep-2015 | Deployment |
14-Oct-2015 | Deployment sign off review |
23-Oct-2015 | Project closure |
- Approved budget
- 72.0 days
- Activity this month
- 5.9 days
- Activity this year
- 5.9 days
- Activity to date
- 54.1 days
- Estimate to complete current year
- 17.9 days
- Estimate to complete future years
- 0.0 days