September 2015
- Report Date
- September 2015
Achievements in Last Period
- Scope change for Service selection page
- Budget increase of 5 days required to carry out the scope change
- Integration testing sign off
Issues
- Services need to be populated from the Service Catelogue to complete UAT. Services are being reviewed as we are populating, hence UAT is a 3 week process.
- Milestones moved due to UAT taking more time than expected
Next Steps
- UAT sign off
- Deployment sign off
Milestones
23-Oct-2015 | Acceptance sign off review |
27-Oct-2015 | Deployment |
10-Nov-2015 | Deployment sign off review |
24-Nov-2015 | Project closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days