October 2015

Report Date
October 2015

Achievements in Last Period

  • Services populated from Service Catelogue
  • UAT started and completed.
  • All JIRAs from UAT closed

 

Issues

  • None

 

Next Steps

  • Deployment (now due on 5th November)
  • Deployment sign off
  • Closure

 

Milestones

19-Nov-2015Deployment sign off review
24-Nov-2015Project closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
72.0 days
Activity this month
5.5 days
Activity this year
20.0 days
Activity to date
68.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
VRS Improvements
Code
COM018
Programme
ISG - Communication (COM)
Project Manager
Chris Konczak
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
09-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
11-Dec-2015
Overall Priority
Normal
Category
Discretionary