October 2015
- Report Date
- October 2015
Achievements in Last Period
- Services populated from Service Catelogue
- UAT started and completed.
- All JIRAs from UAT closed
Issues
- None
Next Steps
- Deployment (now due on 5th November)
- Deployment sign off
- Closure
Milestones
19-Nov-2015 | Deployment sign off review |
24-Nov-2015 | Project closure |
- Approved budget
- 72.0 days
- Activity this month
- 5.5 days
- Activity this year
- 20.0 days
- Activity to date
- 68.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days