August 2015

Report Date
August 2015

Achievements in the Last Period

  • The project has been successfully completed and closed.

Issues

  • None

Next steps

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
66.0 days
Activity this month
5.9 days
Activity this year
5.9 days
Activity to date
54.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IDM Database Migration to Oracle 11G
Code
COM019
Programme
ISG - Communication (COM)
Project Manager
Colin Forrest
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
27-Apr-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Aug-2015
Overall Priority
Normal
Category
Compliance