October 2015

Report Date
October 2015

DSOR and closure were delayed by request of Project Sponsor to allow content to be added by IS Corporate and launch site to IS Staff.

Achievements in Last Period

  • DSOR approved.
  • Service Management Team Manager agreed responsibilities for support with Applications Management (documented in Deployment Checklist with link to OLA).
  • Closure review completed and approved.
  • Project closure approved.

 

Issues

  • No outstanding issues.

 

Next Steps

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SharePoint Digital Space for IS Consolidation
Code
COM020
Programme
ISG - Communication (COM)
Project Manager
Colin Watt
Project Sponsor
Jo Craiglee
Current Stage
Close
Status
Closed
Start Date
10-Jul-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Oct-2015
Category
Discretionary