Continual Service Improvement work on the IDM, adding and amending functionality in response to changing needs of data providers and consumers, as well as targeted improvements to address bugs or other problems.

 

IDM Prioritised Fixes

This project is to resolve known issues on the IDM service and responding to changing business environment. There are a number of Known Errors held on JIRA which require development and are likely to change in response to consultation with stakeholders and operational issues

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2016 BLUE 50.0 days 48.1 days 0.0

Project Info

Project
IDM Continuous Improvement
Code
COM021
Programme
ISG - Communication (COM)
Project Manager
Karen Stirling
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
02-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Apr-2016
Overall Priority
Normal
Category
Discretionary