Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for April 2017 April 2017 GREEN GREEN GREEN BLUE
Report for September 2016 September 2016 GREEN GREEN GREEN GREEN
Report for August 2016 August 2016 GREEN GREEN GREEN GREEN
Report for July 2016 July 2016 GREEN AMBER GREEN AMBER
June 2016 June 2016 AMBER AMBER GREEN GREEN
May 2016 May 2016 GREEN GREEN GREEN GREEN

Project Info

Project
Enterprise API Foundation (COM027)
Code
COM027
Programme
Digital Transformation - Enterprise APIs (DTIP03)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
09-May-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary