Report for April 2017
- Report Date
- April 2017
Achievements in Last Period
- Design Review complete
- Attendance Recording app / demonstrator build started
Issues
None in this reporting period.
Next Steps
- Complete build of attendance Recording app / demonstrator
- Complete UAT
Target Date | Title |
---|---|
09-May-2017 | Scope Change 9 - Acceptance Sign-Off Review |
16-May-2017 | Scope Change 9 - Delivery |
30-May-2017 | Closure |
- Approved budget
- 95.0 days
- Activity this month
- 5.6 days
- Activity this year
- 73.7 days
- Activity to date
- 89.0 days
- Estimate to complete current year
- 6.0 days
- Estimate to complete future years
- 0.0 days