Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • Design Review complete
  • Attendance Recording app / demonstrator build started

Issues

None in this reporting period.

Next Steps

  • Complete build of attendance Recording app / demonstrator
  • Complete UAT
Target Datesort descending Title
09-May-2017 Scope Change 9 - Acceptance Sign-Off Review
16-May-2017 Scope Change 9 - Delivery
30-May-2017 Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
95.0 days
Activity this month
5.6 days
Activity this year
73.7 days
Activity to date
89.0 days
Estimate to complete current year
6.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enterprise API Foundation (COM027)
Code
COM027
Programme
Digital Transformation - Enterprise APIs (DTIP03)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
09-May-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary