June 2016

Report Date
June 2016

Achievements in Last Period

  • Agreement that technical build can be executed without involvement from business.
  • Preliminary discussions about how developed services could be utilised undertaken.
  • High level estimate received and meeting to break this down into finer detail planned.

 

Issues

  • Availability of key resource has impacted completion date of planning milestone and may impact those scheduled in future.

 

Next Steps

  • Devise suitably detailed estimate for effort.
  • Devise plan with milestones.
  • Agree (via Project Sponsor) which API's will be developed.
  • Schedule regular checkpoint meetings.

 

Milestones (adjusted - see associated PICCLE).

Date

Milestone

06-Jul-2016

Planning Complete

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Enterprise API Foundation (COM027)
Code
COM027
Programme
Digital Transformation - Enterprise APIs (DTIP03)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
09-May-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary