Report for August 2016

Report Date
August 2016

Achievements in Last Period

  • Project estimates agreed by project team.
  • Agreed with Student Systems that a process and associated functionality in the API is required before the Student Systems API can be deployed.
  • Agreed that the project will deploy one API (Events Booking), and may develop further and deploy a second API only if project budget allows. 
  • TAD signed-off; 6 new VM's required.
  • Planning complete - approved by WIS 26/8/16.  News item prepared.
  • 10 funded days added to the COM programme for the COM027 project to deliver improvements to the Event Booking API.
  • ADA for Events Booking circulated for review.

Issues

  • Changes to milestones to allow additional time to communicate with key stakeholders were approved by WIS 5/8/16.  Further to the WIS meeting, and as part of the Planning phase, major milestones were replanned to take into account the delay in completion of Planning, and are around 3 weeks behind the previously communicated dates.  This is agreed with the Project Sponsor.

Next Steps

  • Design Review.
  • Start build.

 

20-Oct-2016Build Review
08-Nov-2016Acceptance sign-off
09-Nov-2016Deploy
16-Nov-2016Deployment Review
24-Nov-2016Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
90.0 days
Activity this month
14.1 days
Activity this year
15.1 days
Activity to date
29.4 days
Estimate to complete current year
58.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Enterprise API Foundation (COM027)
Code
COM027
Programme
Digital Transformation - Enterprise APIs (DTIP03)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
09-May-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary