Report for August 2016
- Report Date
- August 2016
Achievements in Last Period
- Project estimates agreed by project team.
- Agreed with Student Systems that a process and associated functionality in the API is required before the Student Systems API can be deployed.
- Agreed that the project will deploy one API (Events Booking), and may develop further and deploy a second API only if project budget allows.
- TAD signed-off; 6 new VM's required.
- Planning complete - approved by WIS 26/8/16. News item prepared.
- 10 funded days added to the COM programme for the COM027 project to deliver improvements to the Event Booking API.
- ADA for Events Booking circulated for review.
Issues
- Changes to milestones to allow additional time to communicate with key stakeholders were approved by WIS 5/8/16. Further to the WIS meeting, and as part of the Planning phase, major milestones were replanned to take into account the delay in completion of Planning, and are around 3 weeks behind the previously communicated dates. This is agreed with the Project Sponsor.
Next Steps
- Design Review.
- Start build.
20-Oct-2016 | Build Review |
08-Nov-2016 | Acceptance sign-off |
09-Nov-2016 | Deploy |
16-Nov-2016 | Deployment Review |
24-Nov-2016 | Closure |
- Approved budget
- 90.0 days
- Activity this month
- 14.1 days
- Activity this year
- 15.1 days
- Activity to date
- 29.4 days
- Estimate to complete current year
- 58.8 days
- Estimate to complete future years
- 0.0 days