Report for September 2016
- Report Date
- September 2016
Achievements in Last Period
- ADA document delivered
- New VMs delivered
- Build in temporary Dev environment underway
- UAT document delivered
- Design and Standards document delivered
- Peer testing has begun on Dev
- List of improvements to the Events Booking API has been prioritised
Issues
- Service documentation is behind schedule
- Delay delivering new VMs has impacted on build / deploy activities (issue 6)
Next Steps
- Complete build / deploy to Dev
- Complete peer testing
- Complete build / deploy to test
- Start UAT
- Demo on Dev (scheduled 27th October)
20-Oct-2016 | Build Review |
08-Nov-2016 | Acceptance sign-off |
09-Nov-2016 | Deploy |
24-Nov-2016 | Deployment Review |
01-Dec-2016 | Closure |
- Approved budget
- 90.0 days
- Activity this month
- 15.5 days
- Activity this year
- 28.9 days
- Activity to date
- 44.2 days
- Estimate to complete current year
- 45.9 days
- Estimate to complete future years
- 0.0 days