Report for September 2016

Report Date
September 2016

Achievements in Last Period

  • ADA document delivered
  • New VMs delivered
  • Build in temporary Dev environment underway
  • UAT document delivered
  • Design and Standards document delivered
  • Peer testing has begun on Dev
  • List of improvements to the Events Booking API has been prioritised

Issues

  • Service documentation is behind schedule
  • Delay delivering new VMs has impacted on build / deploy activities (issue 6)

Next Steps 

  • Complete build / deploy to Dev
  • Complete peer testing
  • Complete build / deploy to test
  • Start UAT
  • Demo on Dev (scheduled 27th October)

 

20-Oct-2016Build Review
08-Nov-2016Acceptance sign-off
09-Nov-2016Deploy
24-Nov-2016Deployment Review
01-Dec-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
90.0 days
Activity this month
15.5 days
Activity this year
28.9 days
Activity to date
44.2 days
Estimate to complete current year
45.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Enterprise API Foundation (COM027)
Code
COM027
Programme
Digital Transformation - Enterprise APIs (DTIP03)
Management Office
ISG PMO
Project Manager
Chris Copner
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
09-May-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary