Report for August 2016
- Report Date
- August 2016
Achievements in the last period
- Project initiated
- Website set up
- Business Analysis started
Issues
No issues to report
Next steps
- Complete planning
- Secure Kofax/SharePoint contractor
- Establish project team/kick off meeting
- Secure scanning vendor
- Approved budget
- 30.0 days
- Activity this month
- 0.5 days
- Activity this year
- 0.5 days
- Activity to date
- 0.5 days
- Estimate to complete current year
- 29.5 days
- Estimate to complete future years
- 0.0 days