Report for September 2016
- Report Date
- September 2016
Achievements in the last period
- Planning competed
- SharePoint contractor secured and started working remotely
- Business Analysis nearing completion
- Scan vendor appointed
- Test scans competed and signed off
- Delivery mechanism for production scanning, agreed, tested and signed off
Issues
-
Microsoft advise that a single library should not contain more that 5000 documents. Due to the number of documents to be stored in the site the SP contractor has recommended a solution based on multiple of libraries. This will mean a new design to the site which IS HR must approve. Given the very tight time scales the idea is to develop an MVP site and improve this in an iterative manner as the project progresses.
Next steps
- Complete and sign off MVP site
- Prepare all documents for uplift
- Start process of importing scanned documents
- Approved budget
- 30.0 days
- Activity this month
- 12.0 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days