Report for November 2016
- Report Date
- November 2016
Achievements in the last period
- SharePoint site configuration complete
- Acceptance Review Milestone achieved
- Scanning and import completed
- Scanner set up and successfully tested
- Documentation drafted, reviewed and signed off
- Handover to Service and Production Management completed
Issues
- No new issues to report
Next steps
- Complete documentation of archiving process
- Deployment Sign Off
- Move to closure
- Approved budget
- 30.0 days
- Activity this month
- 9.5 days
- Activity this year
- 37.0 days
- Activity to date
- 37.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days