Report for December 2016

Report Date
December 2017

Achievements in the last period

  • Some progress made on archiving process
  • Deployment Review Milestone completed 

Issues

  • No new issues to report

Next steps

  • Complete documentation of archiving process
  • Update user documentation on site
  • Draft closure report
  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
40.0 days
Activity this month
9.0 days
Activity this year
38.0 days
Activity to date
38.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Document Management for IS HR
Code
COM030
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
David Anderson
Current Stage
Close
Status
Closed
Start Date
25-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Jan-2017